Change Notice – Installation of Handle with Knob for Kitchen Doors

Kitchen Cabinet
Kitchen Cabinet

At Levels 80 to 94

M/s xxx Constructions and Operations                            

Office No,. xxx,

Financial Tower, DIFC xxx

Tel: xxx

Fax: xxx

Attention          :   Mr. xxx

                            Project Manager                    

Project             :  xxx – 6B+G100 Floors-Hotel & Residential Tower

Client               :  M/s xxx Holdings Ltd

Consultant       :  M/s xxx Architectural & Engineering Consultants)

Subject            :           Change Notice – Installation of Handle with Knob for Kitchen Doors

At Levels 80 to 94

Dear Mr. Ibrahim,

We are in receipt of your letter reference xxx dated 27th June xxx along with the letter from M/s xxx reference xxx dated 25tth June xxx regarding the change notice for the installation of handle with knob for Kitchen Doors of levels 80 to 94.

Please be informed that there will be cost implication of AED xxx to carry out the works, however, due to our very good working relationship with xxx and to our commitments to complete the works, the aforementioned cost will be waived.

This is for your information, reference and record.

Kind Regards,

For xxx Interiors LLC

xxx

Project Manager                                                                                    

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version