Date            : xxx                             

Ref               : CC/DESTEC/014

To                 : M/s. xxx GROUP, PO Box 47395, Sharjah UAE.

Project          : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai.

Subject        : Acceptance of LPO as well as program of work and approval for Pelmet

Dear Mr. xxx,

With reference to the above subject we would like to inform you that we did not received any acceptance of our LPO for pelmet and you did not submit till dated the following:

  1. Acceptance of LPO Nomination.
  2. Shop Drawing
  3. Materials Approval
  4. Program of Work.

Kindly provide as requested immediately.

Regards,

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version