3rd floor partition drawing issue and latest instructions

Requirement of approved material submittals for partition wall

Requirement of approved material submittals for partition wall

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding 3rd floor partition drawing issue and latest instructions

Dear Sir,

With reference to the above, we have been prepared the partition drawing as per your previous approval for the 2nd floor and kindly note the following:

  1. As we discussed during the meeting held on 06.03.17, you have been instructed that we should prepare the drawing for partition as per our original contract scope because issue of variation and client’s concern So, we are holding the drawing to submit as per the concept approved for 2nd floor.

As per new instruction to prepare the shop drawing based on the tender drawing, the double shutter door in a single frame cannot be fixed because of the thickness of frame required and wall thickness are not same. (Existing wall thickness 122mm in mock up room which will be revised 100mm as per tender drawing.)

This is for your kind information, kindly provide a formal instruction to start the shop drawings as per discussion held in the site meeting and review ther issue of the double shutter door and advise accordingly.

Regards,

For xxx Contracting L.L.C.