Date: xxx Ref.: xxx Total Pages: 1 To, xxx Attention: xxx Project: xxx. Subject: Request to add the Contractor’s point/concern in Minutes of Meeting Reference: MCM/AAZ/OCAC/04/2019 dated 26th November 2019 MCM/AAZ/OCAC/05/2019 Reminder -1 dated 8th December 2019 MCM/AAZ/OCAC/05/2019 dated 24th December 2019 MCM/AAZ/OCAC/07/2019 dated 6th January 2020 MCM/AAZ/OCAC/12/2019 dated 19th January 2020 Dear… Continue reading Request to add the Contractor’s point/concern in Minutes of Meeting
Month: December 2020
Delay in Nomination of Provisional Sum & Prime Cost Subcontractors
Date: xxx Ref.: xxx Total Pages: 1 To, xxx Attention: xxx Project: xxx. Subject: Delay in Nomination of Provisional Sum & Prime Cost Subcontractors Reference: MCM/AAZ/OCAC/04/2019 dated 26th November 2019 MCM/AAZ/OCAC/05/2019 Reminder -1 dated 8th December 2019 MCM/AAZ/OCAC/05/2019 dated 24th December 2019 MCM/AAZ/OCAC/07/2019 dated 6th January 2020 Dear Sir, With reference to above… Continue reading Delay in Nomination of Provisional Sum & Prime Cost Subcontractors
Interim Extension of Time Claim (EOT-01)
Date: xxx Ref.: xxx Total Pages: 1 To, xxx Attention: xxx Project: xxx. Subject: Interim Extension of Time Claim (EOT-01) Dear Sir, With reference to the above-mentioned subject, we are hereby submitting Interim Extension of Time Claim to complete of the Project. Delay events arose due to late issuance of revised drawing for first… Continue reading Interim Extension of Time Claim (EOT-01)
Aluminum Windows & False Ceiling height for Ground & First Floor
Date: xxx Ref.: xxx Total Pages: 1 To, xxx Attention: xxx Project: xxx. Subject: Aluminum Windows & False Ceiling height for Ground & First Floor Dear Sir, This is further to our email dated 8th November 2019 (attached), letter Ref. MCM/AAZ/OCAC/04/2019 dated 26th November 2019 (attached) and minutes of site progress meeting 8-13 in… Continue reading Aluminum Windows & False Ceiling height for Ground & First Floor
Works stopped at site due to inclement weather condition – Notification
Date: 12th January 2020 Ref.: xxx Total Pages: 1 To, xxx Attention: xxx Project: xxx. Subject: Works stopped at site due to inclement weather condition – Notification Dear Sir, With reference to the aforementioned subject, we would like to put on record that due to current inclement weather condition all kind of construction works… Continue reading Works stopped at site due to inclement weather condition – Notification