Revised RCP

False ceiling work

False ceiling work

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject:                 Revised RCP

Dear Mr. Loh,

We have received today the revised Reflected Ceiling Plans under Aconex Transmittal Reference: xxx attaching Mace letter to xxx dated 14th October xxx.

We would like to call for a conference call tomorrow around 11 a.m. to discuss this issue further and try to avoid such changes at this stage.  Our Technical & Design Manager Mr. xxx Hansen will call Mr. xxx at that time.

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       