Our Ref:  xxx

Date: xxx

To                           : xxx Contracting LLC

                                  P.O. Box xxx

  Dubai, U. A. E.

Attention            : Mr. xxx

Project                 : xxx at Jumeirah First, Dubai

Subject                 : Required Work Program

Dear Mr. Neel,

We refer to your letter Ref: xxx dated 10th of October xxxx and the subsequent discussions during our meeting on Sunday, the 13th of October xxxx.  Please find below our comments and proposal.

  1. Program
  2. The program you have sent to us shows a start of delivery on 17th of October xxxx.  This date is not realistically achievable.

Yours faithfully,

On behalf of xxx LLC

xxx

Projects Manager