Reply – Continuous Delays in Raising Material Inspection

Reply - Notice of Delay

Reply - Notice of Delay

Our Ref: xxx

Date: xxx

To                    :           xxx Middle East,

                                    P.O.Box xxx,

            Dubai – UAE.

Attention          :           Mr. xxx

                        :           Project Manager

Project             :           xxx Towers Project, Dubai

Subject:                Reply – Continuous Delays in Raising Material Inspection

Dear Mr. Yang,

We received your letter after office hours on 15th January xxx regarding the continuous delay in Raising Material Inspection. We request you to Please refer to all our letter Ref: xxx, Ref: xxx, Ref: xxx, regarding the Marbles which was send earlier to xxx for an action and record.

Further to that we would like to address your letter as follows,

Xxxx did all what can be done to resolve the marble issue.

We are going in rounds for months with no progress. If you know there’s a simple solution, please lead us into it! 

The problem is clear: The agreed PC rate is not enough to satisfy the current requirement of the client. 

Trying to put the blame on Xxxx will not work and will just delay the solution. Xxxx is doing all what it can within the constraints.

Note: Please see attached Log for the MIR raised so far for your information and record.

Yours faithfully,

On behalf of  xxx LLC

xxx

Project Manager       