Regarding to complete balance work, DCD inspection and issue

of cradle rent to complete balance work  

Date: xxx

Ref. xxx

To:                     M/s. xxx , Metal Wowks

Project:              2B + G + 14 + Lower Roof Hotels Building on Plot No. xxx at Barsha, Dubai

Subject:Regarding to complete balance work, DCD inspection and issue of cradle rent to complete balance work  

Dear Mr. Sajith,

With reference to above  and our repeated  follow up  that we are paying cradle rent for your work  since long time ,still aluminium work pending and we want to put your kind notice  that:

  1. As per discussion, you are willing to do pending   Elevation work latter on, we have query that how you will execute balance work, if we will remove the cradle?

Kindly provide your clearance for cradle removal please give us in written confirmation that you will manage your work with your cradle.

So, this is serious issue financially as well as project delay due to pending aluminum work in elevation   and you did not to complete the high level work which required cradle and still balance and client insisting to remove the cradle for DCD.

Regards,
For xxx Contracting L.L.C

xxx

Project Manager