Fire Rating

Fire Rating

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding nomination for joinery sub-contractor and our concern for fire rating.

Dear Sir,

With reference to above ,we would like to inform you that we have reviewed the nomination documents of doors and would like to intimate the following.

  1. The doors quantity must be as per final approved drawing to cross check the quantity.

So, we are intimating to look into this matter and instruct sub-contractor to review final drawing as well as DCD approved drawing for required fire rating.

Regards,

For xxx Contracting L.L.C.