Method Statement Title: Installation of Lightning Protection system

METHOD STATEMENT FOR EARTHING SYSTEM INSTALLATION

METHOD STATEMENT FOR EARTHING SYSTEM INSTALLATION

Method Statement Title: Installation of Lightning Protection system

1.0      Scope :

  1. This method statement details the method for installation of lightning protection system.   

2.0      Material :

Material used for the system is as per BS 6651 : 1992. 

3.0      Applicable locations :

            Roof, Basement, and ground level network. 

4.0      Method :

Material shall be stored in a covered/dry space at all the time to avoid corrosion. 

4.2       Preparation :

4.3       Installation :

4.3.11   Connection between down conductor and earth pits

a.         Blinding, water proofing and 50mm (min) protective screed needs to be provided by Civil contractor.

b.         Refer attached sketch showing sectional view of the earth connection and its assembly.

5.1        Inspection request duly signed-off NMX and Consultant.

6.1       Typical installation details – Detail A – Sheet 1                                                      Detail B – Sheet 2    