METHOD STATEMENT SURFACE MOUNTED LIGHTING FIXTURES

METHOD STATEMENT FOR LIGHTING FIXTURES INSTALLATION

METHOD STATEMENT FOR LIGHTING FIXTURES INSTALLATION

TABLE OF CONTENTS

  1. Scope / Objective
  1. Safety Lighting
    1. Task Lighting
    1. Emergency Arrangements
      1. General
      1. Fire Precautions
      1. Communication
    1. Risks Control
  2. Hazards / Risks
  3. Control Measures / Permits
  4. 3rd Party Protection
  5. Environmental Considerations
  6. Definitions
  1. House Keeping
  1. Manpower Requirement & Supervision
  1. Material Requirement
  1. Plant & Equipment
    1. General
    1. Plant and Equipment Schedule
    1. Personnel Protective Equipment
    1. Power
    1. Working Platforms
  1. Q.C. Approvals and other Documentation
  1. Supporting Documentation
  1. Distribution
  1. Other Information
  1. Site Safety Engineers Approval
  1. Attachment
    1.0    Revision Status
 Revision NoDatePrepared ByReviewed ByArabtech Approved  Revision Description 
 015/03/05    S.Georgiou   C.Ctorides  K.Marnerides                                                                                                                                                                                                 M.Pickup  
 119/04/05    S.Georgiou   C.Ctorides  K.Marnerides                                                                                                                                                                                                 M.Pickup  
 216/05/05    S.Georgiou   C.Ctorides  K.Marnerides                                                                                                                                                                                                 M.Pickup  
        
        
        
            

1.0     SCOPE / OBJECTIVES

This Method Statement covers the installation of Surface Mounted Lighting Fixtures. This procedure is to define the method used to ensure that the Surface Mounted Lighting Fixtures have been installed as per the contract requirement.

  Section 1105/SP/E-16510

2.2   General Specification Requirements 16005, 16010, 16050

Work will be carried out only when all associated works of Main Contractor been verified as completed.

4.0       HEALTH AND SAFETY HAZARDS.

Health and Safety procedure by Main Contractor and by A&P will be implemented for this job. The responsible Safety Officer for each building will conduct regular safety inspection.

  1. Safety Lighting.

Safety lights will be used in case of power failure ensuring the good illumination of the working area to aid evacuation if necessary.

  1. Task Lighting.

Adequate lighting will be provided ensuring the good illumination of the working area. Task lighting, where required will consist of tripod mounted fluorescent light.

  1. Emergency Arrangements.
  1. Risk and Controls.

5.0       DEFINITIONS

              ATC  –           Arabtec Construction (LLC.)

              A&P –           A&P Paraskevaides and Partners LLC.

              M.S. –            Method Statements.

              I.T.P –            Inspection and Test Plan

6.0     RESPONSIBILITIES / SUPERVISION

8.1       Tradesmen who will be used to perform the described work will be experienced electricians. If deemed necessary specific teams / individuals will undergo further training by the Production / Quality Assistance Departments.

Normal working hours: 7.00 a.m to 5.00 pm

  1. HOUSE KEEPING

A&P personnel will clear work areas of waste materials derived from their work on a daily basis ensuring a clean and healthy work environment and also to maintain free access and egress in the event of an emergency.

  1. MANPOWER REQUIREMENT & SUPERVISION

The minimum manpower requirement for installing a surface mounted lighting fixture is one skilled electrician. Typically this activity will involve teams of 5 or 6 electricians working on a floor, under the supervision of a chargehand or foreman, working on a floor to complete luminaire installation for that floor.

  1. MATERIAL REQUIRMENT

Material requirement for this activity are: Lighting Fixtures, Lamps.

  1. PLANT & EQUIPMENT REQUIREMENTS
  1. General: Screw drivers, Wire Strippers, Wire Cutters.
  2. Personnel Protective equipment:  All personnel should wear at all time safety shoes, helmet and coverall, protective glasses and gloves.
  3. Power: Single-phase normal power where it is needed.
  4. Step Ladders.
  1. Q.C. APPROVAL AND OTHER DOCUMENTATION
  1. SUPPORTING DOCUMENTATION
  1. DISTRIBUTION
  1. OTHER INFORMATION

Not applicable

  1. SITE SAFETY ENGINEER’S APPROVAL

Signed on behalf of ATC                                             

  1. ATTACHMENTS