METHOD STATEMENT ISOLATORS

METHOD STATEMENT ISOLATORS

METHOD STATEMENT ISOLATORS

TABLE OF CONTENTS

  1. Scope / Objective
  1. Safety Lighting
    1. Task Lighting
    1. Emergency Arrangements
      1. General
      1. Fire Precautions
      1. Communication
    1. Risks Control
  2. Hazards / Risks
  3. 3rd Party Protection
  4. Environmental Considerations
  5. Definitions
  1. House Keeping
  1. Manpower Requirement & Supervision
  1. Material Requirement
  1. Plant & Equipment
    1. General
    1. Plant and Equipment Schedule
    1. Personnel Protective Equipment
    1. Power
    1. Working Platforms
  1. Q.C. Approvals and other Documentation
  1. Supporting Documentation
  1. Distribution
  1. Other Information
  1. Site Safety Engineers Approval
  1. Attachment – Sketches


    1.0    Revision Status
 Revision NoDatePrepared ByReviewed ByArabtech Approved  Revision Description 
 05/10/04    S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 121/10/04S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 216/11/04S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
 316/12/04S.Georgiou   C.Ctorides  G.GeorghiouM.Pickup  
        
        
            


1.0     SCOPE / OBJECTIVES

This Method Statement covers the installation of Isolators. This procedure is to define the method used to ensure that the Isolators have been installed as per the contract requirement.

Work will be carried out only when all associated works of main contractor been verified that they have been completed.

4.0       HEALTH AND SAFETY HAZARDS.

Health and Safety procedure by Main Contractor and by A&P will be implemented for this job. The responsible safety officer as per A&P procedure will do a routine safety inspection.

  1. Safety Lighting.

Safety lights will be used in case of power failure ensuring the good illumination of the working area to aid evacuation if necessary. To be provided by A&P.

Adequate lighting will be provided ensuring the good illumination of the working area. The task lighting will get power supply from the nearest power socket (provided by main contractor) which should be protected by relevant RCD.

  1. Risk and Controls.

5.0       DEFINITIONS

              ATC  –           Arabtec Construction (LLC.)

              A&P –           A&P Paraskevaides and Partners LLC.

              M.S. –            Method Statements.

6.0     RESPONSIBILITIES / SUPERVISION

8.0           TRAINING

8.1       The tradesmen who will be used to perform the described work will be experienced electricians. If deemed necessary specific teams / individuals will undergo further training by the Production / Quality Assistance Departments.

9.0           WORKING HOURS

Normal working hours: 7.00 a.m to 5.00 pm

  1. HOUSE KEEPING

A&P personnel will clear work areas of scrap materials derived from their work on a daily basis ensuring a clean and healthy work environment and also to maintained free access and egress in the event of an emergency.

  1. MANPOWER REQUIREMENT & SUPERVISION

The manpower requirement for the supervision & installation of the isolators / motor starters is one (1No) electrician and one (1No) laborer.

  1. MATERIAL REQUIRMENT

Materials requirements for this activity are: Screw driver, raw-bolt, screws, hammer, and marker.

  1. PLANT & EQUIPMENT REQUIREMENTS
  1. General: Markers, drills, hammer, pliers, screwdriver.
    1. Plant and equipment schedule: Ditto
      1. Personnel Protective equipment:  All personnel should wear at all time safety shoes, helmet and coverall
        1. Power: Single-phase normal power where it is needed.
          1. Working Platforms: Scaffolding and ladders as per requirements.
  1. Q.C. APPROVAL AND OTHER DOCUMENTATION
  1. SUPPORTING DOCUMENTATION

Shop drawings.

  1. DISTRIBUTION
  1. OTHER INFORMATION

Not applicable

  1. SITE SAFETY ENGINEER’S APPROVAL

Risk mitigation measures as identified in Risk Assessments in Section 19 to be inspected at regular intervals through out the duration of activity. 

  1. ATTACHMENTS