Delay #2 in releasing progress payment

Engineer's Instruction

Engineer's Instruction

Our Ref: xxx

Date:

To

xxx Contracting LLC

P. O. Box xxx

Dubai, U.A.E.

Attention            : Mr. xxx, Group Procurement Manager

Project                 : xxx Phase 2

Subject                 : Delay #2 in releasing progress payment

Dear Sir,

We refer to the terms of our Subcontract PART II – Clause 16.3 “Payment Due” and notify you that you are in default in releasing our progress payment against IPA for month of October xxx.

As of this date, the L/C has still not yet been established by BGC to allow M/s xxx (Contractor Name) to process L/C documents, and on the other hand, the certification and L/C documents due on 4 November xxx (15 days from IPA) have still not been released.  Your delay in releasing the progress payment L/C documents, including certification, is now 32 days.

Accordingly, we reserve our rights for an Extension of Time (EOT) equivalent to the same number of days by which the L/C documents (progress payment) is now delayed.

We have now completed 100% of the project without having received any payment from BGC.

This has severely impacted our cash flow and substantially affected our supply chain and our production process. You are therefore requested to immediately release overdue payments to avoid further disruptions.

All rights are reserved

Yours faithfully,

On behalf of xxx LLC                                                                      

xxx

project Manager