Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Notice of Short Certification References: a) Main Contractor’s letter: xxx dated 28 January xxx b) M/s xxx (Contractor Name) letter… Continue reading Notice of Short Certification
Month: September 2023
Notice of Short Certification
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Notice of Short Certification References: a) Main Contractor’s letter: xxx dated 28 January xxx b) M/s xxx (Contractor Name) letter… Continue reading Notice of Short Certification
Rejection to Notice of Deduction for pods alignment issue.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Rejection to Notice of Deduction for pods alignment issue. Dear Sir, We are in receipt of your letter reference xxx dated 17… Continue reading Rejection to Notice of Deduction for pods alignment issue.
Re- Notification of variation claim supply & installation of additional condensate drainpipe in pod area
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Re- Notification of variation claim supply & installation of additional condensate drainpipe in pod area References: a) xxx dated 18 August xxx… Continue reading Re- Notification of variation claim supply & installation of additional condensate drainpipe in pod area
Pods Handing Over to the Main Contractor
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Pods Handing Over to the Main Contractor References: a) Main Contractor’s letter: ASC/J-259/SUB-COR/371/22 dated 28 January xxx b) M/s xxx… Continue reading Pods Handing Over to the Main Contractor
Completion of Pods Delivery.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Completion of Pods Delivery. Dear Sir, We are writing to inform you that we have successfully completed on 27 February xxx… Continue reading Completion of Pods Delivery.
Response to allegations of delay in delivery and installation of pods.
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Response to allegations of delay in delivery and installation of pods. Dear Sir, We are in receipt of your letter reference:… Continue reading Response to allegations of delay in delivery and installation of pods.
RE – Notice to Restart the Production and Delivery of Pods for xxx – 4
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: RE – Notice to Restart the Production and Delivery of Pods for xxx – 4 Reference: a) M/s xxx (Contractor… Continue reading RE – Notice to Restart the Production and Delivery of Pods for xxx – 4
Instruction to stop production of pods
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Instruction to stop production of pods Reference: a) M/s xxx (Contractor Name) Letter xxx dated 12 December xxx b) M/s… Continue reading Instruction to stop production of pods
Instruction to stop production of pods
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject: Instruction to stop production of pods Reference: a) M/s xxx (Contractor Name) Letter xxx dated 12 December xxx Dear Sir, We… Continue reading Instruction to stop production of pods